Arts + Entertainment
Live Performances
Museums + Art Displays
Pop-Ups
Signage
Studios + Sound Stages
TV + Film Production
Theaters
Theme Parks + Playplaces
discover
Education
Colleges + Universities
Private + Specialty Schools
Public K-12
discover
Energy
Solar Energy
Transmission Infrastructure
Wind Energy
Oil + Gas
discover
Government
Municipal
State
Federal
discover
Healthcare
Senior Care
Hospitals
Outpatient Facilities
discover
Industrial
Heavy Industrial
Warehouse + Distribution Centers
Industrial Ports + Terminals
discover
Ports + Coastal
Berths, Piers + Wharves
Bulkheads
Esplanades
Ferry Landings, Ship Terminals
Floating Structures
Ports + Terminals
Marinas + Breakwaters
Transfer Stations
discover
Public Infrastructure
Bikeways + Trails
Garage + Parking Facilities
Park + Recreational Spaces
Streetscapes
Utility Infrastructure
Water + Wastewater
discover
Real Estate Development
Commercial
Community Facilities
Mixed-Use
Multifamily Residential
discover
Transportation
Airports
Bridges
Ports + Terminals
Rail Transportation
Roads + Highways
Ropeway + Linear Infrastructure
discover
Floating Harbor Wetland
Multimodal Processing Plant
416 + 420 Kent Dynamic Highrise
Wittpenn Bridge
Tiffany Crane
LaGuardia Airport Terminal B
NYC Ferry
Orlando Airport LED Displays
A leading full-service engineering firm renowned for our trusted, high quality, and innovative approach to solving complex challenges.

LIRR Bridge Replacement at Post Ave

McLaren Engineering Group provided bridge engineering design services for this $9.7 million LIRR bridge replacement project at Post Avenue in Westbury, NY. As part of the Long Island Rail Road (LIRR) upgrades, the Third Track project was approved to add a tertiary track to 9.8 miles along the congested Main Line of the LIRR between Floral Park and Hicksville. The first completed project initiative since the Main Line Expansion Project has been the Replacement of the Post Avenue Bridge in Westbury, NY.

Originally built in 1914, The LIRR Post Avenue Bridge was a 63-foot single span structure carrying two tracks supported by steel thru plate girders with a concrete deck and reinforced abutments made of concrete. The 100+ year structure has been a conduit for train traffic that cars and buses pass under with an original roadway clearance of only 11 feet 10 inches. The dimensions had made it extremely vulnerable to vehicular strikes, particularly from trucks failing to clear the underpass. Although still considered in good condition, the bridge was struck over 80 times, causing numerous train and roadway delays in both directions.

LIRR Bridge Replacement with Track Addition

McLaren Engineering Group in association with Halmar International was awarded the $9.7 million LIRR design-build contract for the replacement of the Post Avenue Bridge. As engineer-of-record, McLaren was responsible for completing the final design by expanding preliminary work developed during the RFP process. McLaren was tasked with designing the replacement of the two-track bridge with a three-track bridge and increasing the vertical clearance to 14 feet to reduce outages. The team effort required extensive planning and precision to keep the project on schedule and within budget.

Five months prior to replacement, the bridge superstructure began to be assembled in a parking lot adjacent to the bridge on temporary shoring towers in order to minimize rail disruptions. As part of this design-build contract, McLaren was responsible for completing the final design in order to provide LIRR with the most economical design with the least amount of impact to the community. The new bridge was installed entirely during a 48-hour weekend track outage. Throughout this meticulously planned 48-hour period, the existing bridge superstructure was rolled out and the new superstructure was rolled into its new position via self-propelled modular transporters (SPMTs) from the adjacent parking lot. Crews from Halmar International, Inc. worked around the clock using a unique construction method with a remote-controlled lifting device. That transporter lifted the 103-year-old bridge, which remained intact after it was cut away from its connection to the abutments, and placed into an adjacent parking lot. The contractor then had to modify the abutments to support the new bridge height. Then, the new bridge was lifted, in its entirety, and put into place over the roadway.

Work was completed in just 36 hours, all timed down to the minute to ensure no disruptions to the first train of the Monday morning rush hour. Additional work to fully complete the project included adjustments to the station platforms, installation of stairs and concrete painting and sealing work. The roadway underneath the bridge is being re-graded to provide improved sight lines for motorists, enhancing safety and meeting the latest design standards and requirements of the New York State Department of Transportation.

Completed Ahead of Schedule

The project was completed ahead of schedule and within budget due to the amount of collaborative planning involved. The LIRR Post Avenue Bridge is now 50 feet wide — 13 feet wider than its predecessor — a width that allowed for a section of third track to be placed with a clearance of 14 feet. Traffic disruptions were minimized and a strategic plan to accommodate commuters during the 48-hour rail shutdown was accomplished. The industry-wide collaboration of many moving parts proved to make the entire project a huge success.

Additional Services

McLaren Engineering Group also provided a transportation system impact study, erosion control design, seismic design, structural reinforcing design, and rock anchor design.

Project News